| Group | Permits | Median days to issue | Middle 50% (days) | Median reported cost | Middle 50% (cost) |
|---|---|---|---|---|---|
| Kitchen or bath (all) | 190 | 69 days | 34 days–125 days | $100,000 | $50,000–$180,000 |
| Kitchen mentioned | 129 | 62 days | 34 days–108 days | $110,000 | $60,000–$192,706 |
| Bath mentioned | 133 | 70 days | 36 days–135 days | $100,000 | $60,000–$183,000 |
By community area (3+ permits)
| Group | Permits | Median days to issue | Middle 50% (days) | Median reported cost | Middle 50% (cost) |
|---|---|---|---|---|---|
| Ashburn | 6 | 128 days | 62 days–147 days | $109,800 | $67,877–$150,000 |
| Auburn Gresham | 3 | 69 days | too few | $75,180 | too few |
| Austin | 4 | 60 days | 24 days–104 days | $115,000 | $35,000–$165,000 |
| East Garfield Park | 3 | 66 days | too few | $65,000 | too few |
| Edgewater | 8 | 80 days | 52 days–101 days | $160,896 | $50,000–$374,059 |
| Forest Glen | 3 | 33 days | too few | $20,000 | too few |
| Hyde Park | 3 | 22 days | too few | $150,000 | too few |
| Irving Park | 7 | 72 days | 54 days–285 days | $125,000 | $64,250–$200,000 |
| Kenwood | 3 | 54 days | too few | $450,000 | too few |
| Lake View | 6 | 96 days | 50 days–166 days | $227,500 | $48,975–$1,520,000 |
| Lincoln Park | 8 | 54 days | 8 days–128 days | $187,500 | $63,750–$279,250 |
| Lincoln Square | 7 | 41 days | 23 days–446 days | $98,198 | $60,000–$150,000 |
| Logan Square | 11 | 89 days | 44 days–295 days | $150,000 | $100,000–$250,000 |
| Morgan Park | 3 | 4 days | too few | $50,000 | too few |
| Near North Side | 15 | 39 days | 19 days–73 days | $147,000 | $85,000–$300,000 |
| New City | 4 | 68 days | 24 days–88 days | $60,000 | $46,250–$130,000 |
| North Center | 4 | 94 days | 30 days–158 days | $62,500 | $33,750–$166,559 |
| North Lawndale | 3 | 29 days | too few | $67,000 | too few |
| Norwood Park | 6 | 62 days | 42 days–71 days | $120,000 | $59,824–$180,500 |
| Portage Park | 5 | 53 days | 27 days–166 days | $125,000 | $91,000–$264,357 |
| Rogers Park | 3 | 15 days | too few | $28,550 | too few |
| South Lawndale | 5 | 86 days | 12 days–298 days | $55,000 | $31,000–$155,000 |
| South Shore | 6 | 103 days | 62 days–372 days | $87,500 | $50,000–$120,000 |
| Uptown | 3 | 71 days | too few | $175,000 | too few |
| Washington Heights | 3 | 775 days | too few | $120,000 | too few |
| West Englewood | 3 | 94 days | too few | $95,000 | too few |
| West Lawn | 3 | 171 days | too few | $60,000 | too few |
| West Ridge | 5 | 100 days | 72 days–112 days | $90,000 | $60,000–$150,000 |
| West Town | 9 | 44 days | 22 days–59 days | $100,000 | $60,000–$287,500 |
| Woodlawn | 3 | 58 days | too few | $85,000 | too few |
Areas with fewer than 3 matching permits are left out. Small samples swing a lot, so read the permit count next to each median.
Real projects
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
Label: contractor-sold prices from one Chicago-area GC, 2025-2026. Totals are rounded to the nearest $500, locations are generalized, and identifying details are removed. Final = original contract + change orders.
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
Real projects (contractor-sold prices from one Chicago-area GC, 2025-2026): 7 kitchen jobs, final sold price median $23,000, range $18,500–$49,000. These are labor/install prices sold to homeowners (including the GC's overhead and profit), not subcontractor costs, from mostly north-suburban jobs. See every project.Typical finish materials (client-paid)
These are the contractor's typical averages across recent projects, not per-job receipts. Homeowners usually buy these directly, so they are on top of the labor/install prices shown here.
- Kitchen: about $55,000 (cabinetry, appliances, countertops, light fixtures, cabinet pulls).
- Bathroom: about $12,000 per bathroom (tile, vanity, mirrors, light fixtures, plumbing fixtures, accessories).
All-in estimate, kitchen: about $78,000 (labor/install median $23,000 + typical finishes $55,000). Bath: no bath-only labor median is published, so only the typical $12,000 per bath finish figure is shown. All-in figures are estimates, not quotes.
Kitchen + bath combined jobs (n=2): $53,000, $75,500. Approximate all-in estimates (labor/install + typical finishes, estimate only): KB-09 $53,000 + $55,000 + 2 × $12,000 ≈ $132,000; KB-10 $75,500 + $55,000 + 1 × $12,000 ≈ $142,500. A bath-only figure isn't shown because the only bath-only job was mostly a repipe (see KB-02). Line items by trade.
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-01 · Kitchen · North suburb · 2026
Kitchen relayout: pantry and soffits removed, sink relocated, new lighting, new hardwood floor in adjoining rooms. Change orders: drain repair, more lighting and drywall.
Final: $29,000 (original contract $23,000 + change orders $6,000). Home type: house/unspecified.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $84,000.
Line items by trade (rounded to $100)
flooring $7,500, plumbing $5,100, drywall $5,000, electrical $3,100, demolition $3,000, carpentry $2,700, painting $2,500
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-02 · Bath · North suburb · 2026
Two bathroom remodels PLUS a whole-home repipe with wall and ceiling restoration. Mostly repipe work, so it's left out of the medians.
Final: $55,000 (original contract $50,500 + change orders $4,000). Home type: house/unspecified.
Finish materials (client-paid): Not applicable (mostly a whole-home repipe; a typical per-bath figure would mislead here).
Known job amounts (partial floor, from invoices): shower glass $2,000 (allowance, already in the final above); shower glass $550 (change order, already in the final above). Total known: $2,550.
Excluded from kitchen/bath medians: mostly a whole-home repipe.
Line items by trade (rounded to $100)
plumbing $19,500, tile $9,200, carpentry $6,500, demolition $5,000, drywall $4,500, painting $4,500, electrical $3,000, shower glass $2,600
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-03 · Kitchen · North suburb · 2026
Kitchen layout change: plumbing, electrical and hood duct rerouted, drywall, adjoining laundry tile, wallpaper. Cabinets and paint by others.
Final: $24,500 (original contract $23,000 + change orders $1,500). Home type: house/unspecified.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $79,500.
Line items by trade (rounded to $100)
electrical $6,500, drywall $4,800, tile $3,000, plumbing $2,300, carpentry $2,200, wallpaper $1,800, hvac mechanical $1,200, flooring $1,200, other $800, appliance install $800
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-04 · Kitchen · Chicago, North Side · 2026
Condo kitchen relayout: soffit removed, sink plumbing and electrical rerouted, hood vented to the exterior, flooring patched. Cabinets and paint by others.
Final: $21,500 (original contract $19,500 + change orders $2,000). Home type: condo.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $76,500.
Line items by trade (rounded to $100)
carpentry $6,000, electrical $5,800, plumbing $2,800, flooring $2,200, hvac mechanical $2,000, other $1,800, demolition $600, exterior $200
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-05 · Kitchen · West suburb · 2025
Kitchen tear-out with new hardwood flooring, backsplash, paint and baseboard. Change orders: stair refinishing.
Final: $18,500 (original contract $17,500 + change orders $1,000). Home type: house/unspecified.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $73,500.
Line items by trade (rounded to $100)
flooring $12,000, demolition $3,800, painting $1,500, tile $800, other $200
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-06 · Kitchen · North suburb · 2025
Kitchen relayout: sink relocated, electrical rerouted, hood vent rerouted, drywall repairs. Paint by others.
Final: $22,000 (original contract $20,000 + change orders $2,000). Home type: house/unspecified.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $77,000.
Line items include options and credits not in the final contract and sum higher than the total. The total is authoritative.
Line items by trade (rounded to $100)
electrical $7,500, plumbing $6,800, drywall $4,200, hvac mechanical $3,500, other $1,800
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-07 · Kitchen · North suburb · 2025
Condo kitchen gut with wall removal, rerouted plumbing, gas, electrical and vent, drywall and paint, plus a small powder room refresh.
Final: $23,000 (original contract $22,000 + change orders $1,000). Home type: condo.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $78,000.
Line items include options and credits not in the final contract and sum higher than the total. The total is authoritative.
Line items by trade (rounded to $100)
electrical $5,600, plumbing $3,800, tile $3,500, demolition $3,400, drywall $2,500, painting $2,500, hvac mechanical $800, carpentry $800, flooring $600
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-08 · Kitchen · North suburb · 2025
Kitchen and dining layout change with wall removal, rerouted gas, plumbing, electrical and HVAC, tile and wood flooring, trim and paint.
Final: $49,000 (original contract $45,000 + change orders $3,500). Home type: house/unspecified.
Finish materials (client-paid): about $55,000 (typical, not job-specific). Approx. all-in estimate: about $104,000.
Line items include options and credits not in the final contract and sum higher than the total. The total is authoritative.
Line items by trade (rounded to $100)
carpentry $12,000, flooring $8,400, demolition $6,500, electrical $6,500, painting $4,500, tile $4,200, plumbing $3,800, windows doors $2,500, hvac mechanical $1,500
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-09 · Kitchen + Bath · Chicago, North Side · 2025
Kitchen island relocation plus a primary bath remodel (tile shower, freestanding tub, heated floor) and a guest bath refresh.
Final: $53,000 (original contract $51,500 + change orders $1,500). Home type: house/unspecified.
Finish materials (client-paid): about $79,000 (typical, not job-specific: kitchen $55,000 + 2 baths × $12,000). Approx. all-in estimate: about $132,000.
Known job amounts (partial floor, from invoices): doors millwork $1,800 (allowance (within labor line), already in the final above). Total known: $1,800.
Line items by trade (rounded to $100)
plumbing $11,000, tile $8,700, demolition $7,000, carpentry $6,000, electrical $5,600, heated floor $4,500, other $3,600, windows doors $2,500, bath refresh $2,000, flooring $1,800, appliance install $500
Labor and install only. These are labor and install prices only. Finish materials the homeowner bought (cabinets, countertops, tile, fixtures, flooring, appliances) are not included, and they often add as much as or more than the labor.
KB-10 · Kitchen + Bath · North suburb · 2025
Whole-floor flooring, new kitchen and bath cabinetry install, primary bath plumbing, tile, heated floor and shower glass. An optional add-on (~$10,500) is excluded from comparisons.
Final: $75,500 (original contract $73,000 + change orders $2,000). Home type: house/unspecified.
Finish materials (client-paid): about $67,000 (typical, not job-specific: kitchen $55,000 + 1 bath × $12,000). Approx. all-in estimate: about $142,500.
Known job amounts (partial floor, from invoices): shower glass $2,000 (allowance, already in the final above); cabinets $6,000 (pass-through deposit, already in the final above); windows $987.80 (material cost (stated), already in the final above). Total known: $8,987.80.
Optional add-on excluded from the total and comparisons.
Line items by trade (rounded to $100)
flooring $24,500, cabinet install $8,500, carpentry $8,000, plumbing $6,000, cabinet deposit $6,000, demolition $5,000, painting $4,500, tile $4,000, electrical $2,500, heated floor $2,200, windows doors $2,100, shower glass $2,000